Enon-Xenia Roadway Project

The construction project will start on January 16, the start date was pushed back a week, hence the date discrepancy in the graphic below. During Phase 1 the intersection of Rebert Pike and Enon-Xenia will remain open. The county engineers plan to install barricades on Enon-Xenia immediately south of Rebert Pike.

 

During Phase 2, the water main near the sidewalk area on the west side of Enon-Xenia in front of the school will be replaced. 

 

Phases 3 and 4 will most likely start after May 31. During these phases, a portion of Enon-Xenia will have one lane of traffic in front of the school for northbound traffic only. The county engineer’s office hopes to have phase 4 complete in early October. 

 

During Phase 5, both lanes of traffic will reopen and the final course of asphalt will be put down.

 

A few routes will be impacted by this construction project - Bus 25 HS, Bus 27 GES, Bus 8 GES, PK-PM Bus 2/22 mid-day. Our Transportation Director, Elmer Beard, has been working with our bus drivers to make adjustments to impacted routes and timing. Although construction is slated to begin on January 16, you may notice your student’s bus routes making slight adjustments next week as our transportation department works out these changes.

If you have questions or concerns please reach out to our transportation department:


Greenon Local Schools Transportation: 937-340-6352  

Elmer Beard, Transportation Supervisor